South Carolina Pipelines Contractor
Sample Questions for the South Carolina Pipelines Contractors Exam
-
When the soils report indicates that compaction of a trench will result in 10% less volume, what should be expected during backfill?
- Fill will have to be exported.
- Soil will have to be imported.
- Water will need to be added to increase compaction.
- More asphalt will be needed during resurfacing.
-
If a 12', 45-degree offset is required when laying a pipeline, how much extra pipe is required in order to avoid the obstruction?
- 5 lf
- 12 lf
- 16 lf
- 24 lf
-
According to OSHA, what should be the minimum distance between ladders inside a trench that is 4' or deeper?
- 25'
- 50'
- 75'
- 100'
-
Straight line depreciation is computed by:
- dividing the value of the asset by the years in the recovery period, and claiming the same deduction every year
- depreciating the asset only to the extent that it is paid for; so if you finance the asset, you can claim a write-off only to the extent that you pay the bank
- taking the expense as a straight line-item write- off in the year purchased
- writing off the asset only over 35 years
-
In an operation including shop work, you could have up to four different types of inventory. These are:
- raw materials, purchased materials, overstock, and finished goods
- raw materials, job-assigned materials, supplied, and all other
- regular inventory, special-order inventory, pending inventory, and supplies
- raw materials, supplies, work in process, and finished goods
Answers: Click Here to show the answers.
1.) b 2.) a 3.) b 4.) a 5.) d