What is the volume of a hole 120 feet long, 30 feet wide, and 6 feet deep?
- 500 cubic yards
- 800 cubic yards
- 1,200 cubic yards
- 1,300 cubic yards
-
What does the term "balanced dirt job" refer to?
- Thorough distribution of aggregate in the soil mix
- Level highway grade work without slopes or ditches
- No excess dirt in cut and fill work
- Proper compaction rate of the grade work
-
How many days does it take for standard portland cement concrete to reach maximum strength?
- 7 days
- 14 days
- 21 days
- 28 days
-
Straight line depreciation is computed by:
- dividing the value of the asset by the years in the recovery period, and claiming the same deduction every year
- depreciating the asset only to the extent that it is paid for; so if you finance the asset, you can claim a write-off only to the extent that you pay the bank
- taking the expense as a straight line-item write- off in the year purchased
- writing off the asset only over 35 years
-
In an operation including shop work, you could have up to four different types of inventory. These are:
- raw materials, purchased materials, overstock, and finished goods
- raw materials, job-assigned materials, supplied, and all other
- regular inventory, special-order inventory, pending inventory, and supplies
- raw materials, supplies, work in process, and finished goods
Answers: Click Here to show the answers.
1.) b 2.) c 3.) d 4.) a 5.) d