Sample Questions for the Hawaii General Builders Exam
-
Which of the following is NOT included in the earthwork stage of construction?
- Excavation and filling to make way for the building
- Backfilling after the building has been built
- Grading preparatory to installing paving, walkways, lawns, and landscaping
- Removal of trees and vegetation
-
What is the MAXIMUM width required for lumber boards used for sheathing?
- 10 inches
- 12 inches
- 8 inches
- 5 inches
-
What is the MINIMUM width required for a residential shower door?
- 22 inches
- 24 inches
- 28 inches
- 30 inches
-
What is the volume of a cylinder if the diameter equals 2 feet and the length equals 4 feet?
- 8 cubic feet
- 12.56 cubic feet
- 25.12 cubic feet
- 50.24 cubic feet
-
High frequency vibration used to compact freshly poured concrete results in which of the following?
- Higher lateral pressures
- Faster curing time
- Lower lateral pressures
- Slower curing time
Answers: Click Here to show the answers.
1.) d 2.) c 3.) a 4.) b 5.) a