Alaska Residential Contractor
Sample Questions for the Alaska Residential Contractors Exam
-
Which of the following is NOT included in the earthwork stage of construction:
- Excavation and filling to make way for the building
- Backfilling after the building has been built
- Grading preparatory to installing paving, walkways, lawns, and landscaping
- removal of trees and vegetation
-
What is the maximum width required for lumber boards used for sheathing?
- 10 inches
- 12 inches
- 8 inches
- 5 inches
-
What is the minimum width required for a residential shower door?
- 22 inches
- 24 inches
- 28 inches
- 30 inches
-
What is the volume of a cylinder if the diameter equals 2 feet and the length equals 4 feet?
- 8 cubic feet
- 12.56 cubic feet
- 25.12 cubic feet
- 50.24 cubic feet
-
High frequency vibration used to compact freshly poured concrete results in which of the following?
- high lateral pressures
- faster curing time
- lower lateral pressures
- slower curing time
Answers: Click Here to show the answers.
1.) d 2.) c 3.) a 4.) b 5.) a