ACI SP-4: Formwork for Concrete, 7th Edition

ACI SP-4: Formwork for Concrete, 7th Edition
Item #: 180-9258-05
Author: M. K. Hurd
Publisher: ACI
ISBN:SP47TH
Format: Paperback
Your Price: $185.95
In Stock


Cover the basics of form design and construction with the new ACI SP-4 7th Edition
This document serves a broad range of information needs with the objective of improving quality, safety, and economy in all types of formwork. For the experienced designer or builder of formwork, it is a ready reference on material properties, design data, and construction suggestions. For the architect or engineer, it adds guidance relating to structural design details and the problems and possibilities of executing them in formwork. For the novice, the book explains basic design principles and provides an introduction to many common formwork practices. This edition includes new material on single-sided wall forms, insulating concrete forms, pressure formulas with coefficients for differing weights and mix chemistries, inflated forming methods, and expanded text on multistory shoring systems. 500 pp.

ACI SP-4: Formwork for Concrete, 7th Edition - Table of Contents:

  • Introduction
  • General Objectives in Formwork Building
    • How Formwork affects concrete quality
    • Causes of failures
    • Planning for Safety
    • Relationship of architect, engineer, and contractor
    • Measurement and payment for formwork
    • How the architect-engineer can reduce form costs
    • References
  • Overall Planning
    • Development of a basic system
    • Key areas of cost reduction
    • Planning for maximum reuse
    • Economical form construction
    • Setting and stripping
    • Other costs affected by formwork plan
    • Planning examples
  • Materials, Accessories, Proprietary Products
    • Lumber
    • Engineered wood products
    • Plywood
    • Other framing and facing materials
    • Insulation and insulating forms
    • Hardware and fasteners
    • Prefabricated forms
    • Shoring and scaffolding
    • References
  • Loads and Pressures
    • Vertical loads
    • Lateral pressure of fresh concrete
    • Lateral loads
    • Other loads
    • References
  • Form Design
    • Notation
    • Basic Simplifications
    • Beam formulas
    • Design criteria
    • Bearing examples
    • Wall, slab and beam form design
    • Form accessories
    • Column form design
    • Shoring and scaffolding
    • Bracing for lateral loads
    • Camber and adjustment for settlement
    • References
  • Design Tables
    • Sheating design
    • Joists, studs, beams
    • Double members
    • Wood shores
    • Form design Using the Tables
    • Design tables
  • Formwork drawings
    • General layout and detail drawings
    • Check list of details
    • Recheck of structural drawings
    • Drawing approval
  • Building and Erecting the Formwork
    • Carpentry Shop and Job Mill
    • Footings
    • Slab on grade and paving work
    • Wall forms
    • Column forms
    • Beam or girder forms
    • Slab forms
    • Shoring and Scaffolding
    • BRIDGE FORMWORK
    • Foundations
    • Piers
    • Pier caps and tie struts
    • Superstructures
    • Arch bridges
    • Segmental box girder bridge construction
    • Making precast bridge segments
    • References

  • Using the forms
    • Placing reinforcement and inserts
    • Preparation for concreting
    • Inspection and form watching
    • Placing and vibrating-effect on formwork
    • Removal of forms and shores
    • Reshoring
    • Care and storage of forms and accessories
    • Cold weather protection
    • References
  • Formwork for Architectural Concrete
    • Specifications: Defining quality
    • Architectural formwork design
    • Exposed concrete surfaces
    • Construction of architectural forms
    • Stripping
    • Cleanup and repair
    • References
  • Shells, Domes, Folded Plates
    • Shell form design considerations
    • Building the forms
    • Placing concrete
    • Form removal
    • Inflated forming methods
    • References
  • Mass Concrete
    • Low lift formwork
    • Handling, erecting, stripping
    • Non-cantilevered formwork
    • Roller-compacted mass concrete
    • Foundations or starting lifts
    • Curing, joint cleanup, insulation
    • Planning and supervision
    • Tolerances
    • References
  • Tunnels and Shafts
    • Tunnel forming components
    • Concrete placement methods
    • General design considerations
    • Form construction
    • Stripping time
    • Tolerances
    • Shafts
  • Special Techniques in Concrete Construction
    • Slipform construction
    • Horizontal slipforms
    • Traveling forms
    • Tilt-up construction
    • Lift method of construction
    • Preplaced aggregate concrete
    • Shotcrete
    • Tremie concrete
    • PRECAST CONCRETE
    • Advantages of precasting
    • Formwork
    • Stripping
    • Erection and joints
    • PRESTRESSED PRECAST CONCRETE
    • Forms for post-tensioning
    • Forms for pre-tensioning
    • References
  • APPENDIX
  • Acknowledgments
  • Glossary
  • Guide to Formwork for Concrete, ACI 347-04
  • ACI 318-03 Code and Commentary-Chapter 6, Formwork, Embedded Pipes, and Construction Joints
  • OSHA Regulations, Subpart Q-Concrete and Masonry Construction
  • Index
  • Metric Conversion Factors

Close Window